Aquatic Center Update 3-10-21

Electrical repairs and upgrades are complete and the larger equipment is being installed, including the main pool motor!

The mechanical room is up-to-code and soon will be revving up the new motor and heating and disinfecting the 180,000 gallons of water in the pool.

The hot tub also received some repairs and got a new motor as well.

If all goes well, and without ANY more surprises, we are hoping to be up to temp by the first week of April. We have not had the opportunity to test the initial repairs to the liner, but with the pool partially filled, and without the pressure of circulating water, those repairs appear to be holding.

We’ll be back in touch with definite re-open dates and any remaining “ Covid” restrictions shortly!